
What to take into your next appraisal
- Separate the project funding gap, debt balance and investor cash at risk.
- Model the facility limit, eligible costs, draw order and interest basis explicitly.
- Reconcile every period and test whether delayed receipts require more equity.
Read the project, the loan and the investor separately
Start with project receipts less project payments before financing. The lowest cumulative balance shows the funding gap on that basis. A loan then supplies part of that gap, but debt is money to repay, not project income. Finally, calculate equity contributions and distributions. These three views explain different things and should reconcile without sharing ambiguous labels such as cash required.
Define peak equity as the maximum cumulative contributions less distributions to the investor. If the model also reports cumulative contributions before distributions, label that separately. A project that returns cash and later calls for more capital can have a different peak net investment from its total cash contributed. Neither measure automatically includes a guarantee, undrawn commitment or another project supported by the same investor.
RICS distinguishes project cash flows from cash flows after financing and cautions that a particular borrowing structure can change the basis of the appraisal. Keep the project result and investor result visible separately when presenting a funding proposal.
Sources: RICS: Valuation of development property, Appendix B1.2.8
Turn the funding agreement into model rules
A facility amount alone is not enough to calculate a draw. Record what expenditure qualifies, when equity must be provided, when a draw can be requested, what evidence releases it and whether repaid amounts can be borrowed again. Also record maturity and the order in which available cash pays costs, interest, principal and distributions. Do not let a balancing formula silently create borrowing that the agreement does not permit.
The OCC commercial real estate lending handbook discusses equity timing, interest reserves and funds needed to finish construction. It is US bank supervisory guidance, not a statement of universal loan terms. Its useful modelling lesson is to examine these items individually against the actual agreement.
- Distinguish a limit on cumulative draws from a limit on outstanding principal.
- State whether interest is paid in cash, drawn from a reserve or added to debt.
- Keep fees, minimum cash and restricted receipts visible where they apply.
- Use the agreed interest periods and day-count basis, including any changes in rate.
Set the rules for a small funding example
Consider an invented development with costs of 12 million and receipts of 15 million in one currency. Time zero is acquisition, followed by four equal quarters. All movements occur at each period end; the schedule does not estimate higher cash requirements within a quarter. Costs include land and development expenditure. Tax, arrangement fees, reserves and cost overruns are excluded to isolate the funding mechanics.
The investor supplies the first 3 million of project costs. A non-revolving loan then funds eligible project costs up to 7 million of cumulative draws. It cannot fund interest, and repaid amounts cannot be redrawn. Any remaining shortfall requires equity. Available receipts pay current project costs and interest first, then repay debt; distributions occur only after those obligations are met.
Interest is 2% of opening principal each quarter, equivalent to an assumed nominal annual rate of 8% with quarterly periods. New end-of-quarter draws accrue interest from the next quarter. Interest is paid, not capitalised. These are chosen example rules, not proposed terms or a market benchmark.
Follow every draw and repayment
At time zero, equity pays 2 million. Quarter 1 needs 4 million: the remaining 1 million of initial equity is used first, followed by a 3 million debt draw. Quarter 2 uses the remaining 4 million loan capacity, but its 0.06 million interest bill requires additional equity. That small top-up is exactly what a simple 3 million equity allowance would miss.
Quarter 3 receipts of 3 million cover costs of 2 million and interest of 0.14 million, leaving 0.86 million to repay principal. Quarter 4 begins with debt of 6.14 million. Interest is therefore 0.1228 million. The final 12 million receipt repays the debt and leaves 5.7372 million for the investor.
| Cash movement, millions | Time 0 | Q1 | Q2 | Q3 | Q4 |
|---|---|---|---|---|---|
| Project receipts | 0 | 0 | 0 | 3.0000 | 12.0000 |
| Project costs | 2.0000 | 4.0000 | 4.0000 | 2.0000 | 0 |
| Equity contributed | 2.0000 | 1.0000 | 0.0600 | 0 | 0 |
| Debt drawn | 0 | 3.0000 | 4.0000 | 0 | 0 |
| Interest paid | 0 | 0 | 0.0600 | 0.1400 | 0.1228 |
| Principal repaid | 0 | 0 | 0 | 0.8600 | 6.1400 |
| Investor distribution | 0 | 0 | 0 | 0 | 5.7372 |
| Closing debt | 0 | 3.0000 | 7.0000 | 6.1400 | 0 |
Reconcile the three different capital numbers
Before financing, cumulative project cash reaches a low of minus 10 million at the end of Quarter 2. Peak debt is 7 million. Peak equity is 3.06 million, including the interest top-up. Adding peak debt and peak equity gives 10.06 million here because both peaks occur together and finance adds a cash cost. Peaks do not necessarily coincide in a more complex project.
Across the full schedule, receipts of 15 million plus equity of 3.06 million plus debt draws of 7 million equal total cash sources of 25.06 million. Uses are project costs of 12 million, interest of 0.3228 million, debt repayment of 7 million and distributions of 5.7372 million. Uses also equal 25.06 million.
The investor receives 5.7372 million after contributing 3.06 million, a surplus of 2.6772 million. That equals the project surplus of 3 million less interest of 0.3228 million. It is an undiscounted cash result. It does not describe the return earned per year or prove that the required capital is available.
Move the receipt and identify who funds the extra time
Now move the final receipt from Quarter 4 to Quarter 5. Hold costs and the interest rate constant. Assume the lender allows the extension without a fee; that is an extra scenario assumption, not an automatic right. Quarter 4 still owes 0.1228 million interest, with no receipt available and no further loan draws permitted. Equity must cover it.
Peak equity rises to 3.1828 million. Another 0.1228 million of interest is paid from Quarter 5 receipts before repayment. Total interest becomes 0.4456 million and the investor surplus falls to 2.5544 million. The final distribution remains 5.7372 million, but it arrives later and follows a larger contribution. A distribution number alone would conceal both changes.
Use peak equity as a funding decision, not just a chart
Ask whether the investor can fund the modelled contributions on their actual dates. Record any amount already spent, cash still to be committed and unused contingency separately. Land contributed by an owner may meet a contractual equity test while providing no cash to pay a contractor. A nominal commitment and immediately available cash answer different questions.
For a Gulf project, inspect the actual facility, permitted use of buyer collections, currency exposure and release conditions. If the funding structure is not an interest-bearing loan, model its contractual payment mechanics directly rather than relabelling this example. Local requirements belong in the project evidence register, not in an assumed regional financing template.
The review should end with a base funding schedule, a delayed-receipt case and a clearly assigned response to the shortfall. A cost increase, an unavailable draw or a repayment brought forward may be the more important test for a particular scheme. Keep each change connected to the agreement or project event that could cause it.
Sources and further reading
- Valuation of development property, Appendix B1.2.8 RICS · Accessed 15 September 2026
- Commercial Real Estate Lending, version 2.0: interest reserves and borrower equity Office of the Comptroller of the Currency · Accessed 15 September 2026
Published by Feasly. How we prepare our guides. Suggest a correction.


